Société Générale (2025)

Signing Date 03 Sep 2007
Region of Headquarters: Europe
Current EPFI Reporting Year/Period: 2025
Institutional Reporting: Link to Report - Link to Additional Report

 

Please read the important notes and disclaimer for further information on ‘EPFI Reporting’, compliance and publication on the EP website.

Further information on this EPFI may be obtained through the Institutional Reporting hyperlink.

Project Finance Advisory Services

Total number mandated in the reporting period: 12

Sector
Mining 2
Infrastructure 5
Oil & Gas
Power 4
Others 1
Sub-Total 12
Region
Americas 2
Europe, Middle East & Africa 9
Asia Pacific 1
Sub-Total 12

Project Finance Transactions

Total number that reached Financial Close in the reporting period: 91

Equator Principles Category A1 B2 C3
Sector
Mining 1
Infrastructure 2 16 2
Oil & Gas 3
Power 10 51 3
Others 2 1
Region
Americas 1 45 3
Europe, Middle East & Africa 9 14 3
Asia Pacific 3 13
Country Designation
Designated Country 4 7 65 6
Non Designated Country 6 7
Both
Independent Review
Yes 13 66 2
No 6 4
Totals 13 72 6
1

Category A – Projects with potential significant adverse environmental and social risks and/or impacts that are diverse, irreversible or unprecedented.

2

Category B – Projects with potential limited adverse environmental and social risks and/or impacts that are few in number, generally site-specific, largely reversible and readily addressed through mitigation measures.

3

Category C – Projects with minimal or no adverse environmental and social risks and/or impacts.

4

Designated Countries are those countries deemed to have robust environmental and social governance, legislation systems and institutional capacity designed to protect their people and the natural environment.

Project-related Refinance & Project-related Acquisition For Project Finance

Total number that reached Financial Close in the reporting period: 1

Sector
Mining
Infrastructure 1
Oil & Gas
Power
Others
Sub-Total 1
Region
Americas
Europe, Middle East & Africa 1
Asia Pacific
Sub-Total 1
Country Designation
Designated Country 1
Non Designated Country
Both
Sub-Total 1

Project Name Reporting For Project Finance (And Project-related Refinance & Project-related Acquisition Finance For Project Finance)

No. Project Name Sector Project Location(s) Year of Financial Close
1 C.P.E.S. SOLEIL ROUGE Power France 2025
2 PE DU HOUARN Power France 2025
3 SPV DEV'ENR 16 Power France 2025
4 El Espino Copper Project Mining Chile 2025
5 HSAGP Energy EV Battery Plan Others United States 2025
6 Casablanca Desalination Project Infrastructure Morocco 2025
7 Haweswater Aqueduct ResilienceProgramme (HARP) Infrastructure United Kingdom 2025
8 PDG TY1 Data Center Campus, Saitama, Japan Infrastructure Japan 2025
9 STACK TKY01 Tokyo Campus Green Financing, Inzai, Japan Infrastructure Japan 2025
10 Project Longtail (ITS) Infrastructure United States 2025
11 Project Big Sky Infrastructure United States 2025
12 Project Snowbird Infrastructure United States 2025
13 STC Campus Infrastructure United States 2025
14 Project Tarpon Infrastructure United States 2025
15 JKT01, JKT02, JKT03,Jakarta, Indonesia Infrastructure Indonesia 2025
16 Port Liberty New York and Port Liberty Bayonne Additional Financing Infrastructure United States 2025
17 Project Flash 2.0 Infrastructure United States 2025
18 Bauxite III Infrastructure United States 2025
19 Udupi-Kasargode Transmission Project Ltd (UKTL) Power India 2025
20 QTS Cedar Rapids DC1, DC2, DC3 Infrastructure United States 2025
21 Project Jupiter Infrastructure United States 2025
22 Hampton DC 1 Infrastructure United States 2025
23 MEL01 Infrastructure Australia 2025
24 AUS-02 Infrastructure United States 2025
25 Fengmiao 1 offshore wind farm Power Taiwan, China 2025
26 Serentica BALCO 200 MW Solar Power India 2025
27 Tagawa BESS Project Power Japan 2025
28 Greater Changhua 2 Power Taiwan, China 2025
29 Calala BESS 1 Power Australia 2025
30 Calala BESS 2 Power Australia 2025
31 SAEL MHP 1- 300 MW Solar Power India 2025
32 Cleanmax Power India 2025
33 Bulabul Battery Stage 1 (formerly Wellington BESS 1) Power Australia 2025
34 Elaine BESS Power Australia 2025
35 Baltica 2 Power Poland 2025
36 Sizewell C Power United Kingdom 2025
37 Al Masa'a Solar Power Plant Power Saudi Arabia 2025
38 Baltyk 2 Power Poland 2025
39 Baltyk 3 Power Poland 2025
40 Project Scoop Power Finland 2025
41 Thorpe Marsh 1.4 GW Battery Storage Project Power United Kingdom 2025
42 Claudia BESS Energy Storage Power France 2025
43 Project Victoria Power Spain 2025
44 BC-Wind Power Poland 2025
45 Starah Wind Power Project Power Saudi Arabia 2025
46 Shaqra Wind Power Project Power Saudi Arabia 2025
47 Al Henakiyah-2 Solar Power Plant Power Saudi Arabia 2025
48 Project Sadawi Power Saudi Arabia 2025
49 Chalk Bluff Solar Project Power United States 2025
50 Intersect's Quantum Portfolio Power United States 2025
51 Taft Project Power United States 2025
52 energyRe’s solar portfolio Power United States 2025
53 Easley Power United States 2025
54 Hashknife Phase II Power United States 2025
55 Blackcomb and Traverse Pipeline Oil & Gas United States 2025
56 Trailblazer Pipeline Conversion Project Oil & Gas United States 2025
57 Project Ferdinand Power United States 2025
58 Trinity Gas Storage Phase II Oil & Gas United States 2025
59 Hedley Project Power Canada 2025
60 Hedley Project Power Canada 2025
61 Country Acres Power United States 2025
62 Snowflake A Power United States 2025
63 Atlas VIII Power United States 2025
64 Project Astoria Power United States 2025
65 Mallard Power United States 2025
66 Chestnut Carbon’s Sustainable Restoration Project Others United States 2025
67 Project Arena Power Chile 2025
68 Project Arenales Power Chile 2025
69 Project Copiapo Power Chile 2025
70 Domeyko Solar + Storage project Power Chile 2025
71 Project Limestone Power Chile 2025
72 Dune+ Power Chile 2025
73 1000 Mile Solar Power United States 2025
74 Three Rivers Solar Power United States 2025
75 Wolf Summit Energy Project Power United States 2025
76 Apache Hill Energy Centre Power United States 2025
77 Repowering of Mount Storm Wind Farm Power United States 2025
78 Big Creek Solar Power United States 2025
79 Jacumba Valley Ranch Power United States 2025
80 Duffy BESS Power United States 2025
81 Tehuacana Power United States 2025
82 Project Atacama Power Chile 2025

Number of projects that were not disclosed as per the disclosure conditions specified in Annex B of the Principles: 11

Under EP4, project name reporting is required for Project Finance transactions that have reached Financial Close and encouraged for Project-Related Corporate Loans that have reached Financial Close.

Project-Related Corporate Loans

Total number that reached Financial Close in the reporting period: 3

Equator Principles Category A1 B2 C3
Sector
Mining
Infrastructure 1 2
Oil & Gas
Power
Others
Region
Americas
Europe, Middle East & Africa 1 2
Asia Pacific
Country Designation
Designated Country 4 1
Non Designated Country 1 1
Both
Independent Review
Yes 1 1
No 1
Totals 1 2
1

Category A – Projects with potential significant adverse environmental and social risks and/or impacts that are diverse, irreversible or unprecedented.

2

Category B – Projects with potential limited adverse environmental and social risks and/or impacts that are few in number, generally site-specific, largely reversible and readily addressed through mitigation measures.

3

Category C – Projects with minimal or no adverse environmental and social risks and/or impacts.

4

Designated Countries are those countries deemed to have robust environmental and social governance, legislation systems and institutional capacity designed to protect their people and the natural environment.

Project-related Refinance & Project-related Acquisition For Project-related Corporate Loans

Total number that reached Financial Close in the reporting period: 0

Project Name Reporting For Project-related Corporate Loans (And Project-related Refinance & Project-related Acquisition For Project-related Corporate Loans)

No. Project Name Sector Project Location(s) Year of Financial Close
1 Hassa‑Dörtyol Highway and Railway Project Infrastructure Turkiye 2025
2 Eastern Green Link 2 (EGL2) Infrastructure United Kingdom 2025
3 Światłowód Inwestycje refinancing Infrastructure Poland 2025

Number of projects that were not disclosed as per the disclosure conditions specified in Annex B of the Principles: 2

Under EP4, project name reporting is encouraged for Project-Related Corporate Loans that have reached Financial Close and required for Project Finance transactions that have reached Financial Close.

EP4 applies for those transactions mandated after 1 October 2020 and that have reached Financial Close by the end of the period being reported.

Implementation of the Equator Principles

Société Générale´s EP implementation reporting is provided at: Equator Principles Implementation Report 2025