Sumitomo Mitsui Trust Bank, Limited (1 Apr 2025 – 31 Dec 2025)
| Signing Date | 01 Feb 2016 |
| Region of Headquarters: | Asia-Oceania |
| Current EPFI Reporting Year/Period: | 1 Apr 2025 - 31 Dec 2025 |
| Institutional Reporting: | Link to Report |
Please read the important notes and disclaimer for further information on ‘EPFI Reporting’, compliance and publication on the EP website.
Further information on this EPFI may be obtained through the Institutional Reporting hyperlink.
Project Finance Advisory Services
Total number mandated in the reporting period: 3
| Sector | |
|---|---|
| Mining | |
| Infrastructure | |
| Oil & Gas | |
| Power | 1 |
| Others | 2 |
| Sub-Total | 3 |
| Region | |
|---|---|
| Americas | |
| Europe, Middle East & Africa | |
| Asia Pacific | 3 |
| Sub-Total | 3 |
Project Finance Transactions
Total number that reached Financial Close in the reporting period: 16
| Equator Principles Category | A1 | B2 | C3 |
|---|---|---|---|
| Sector | |||
| Mining | |||
| Infrastructure | 1 | ||
| Oil & Gas | |||
| Power | 1 | 13 | |
| Others | 1 | ||
| Region | |||
| Americas | 3 | ||
| Europe, Middle East & Africa | 1 | 10 | |
| Asia Pacific | 1 | 1 | |
| Country Designation | |||
| Designated Country 4 | 5 | 1 | |
| Non Designated Country | 1 | 9 | |
| Both | |||
| Independent Review | |||
| Yes | 1 | 14 | 1 |
| No | |||
| Totals | 1 | 14 | 1 |
Category A – Projects with potential significant adverse environmental and social risks and/or impacts that are diverse, irreversible or unprecedented.
Category B – Projects with potential limited adverse environmental and social risks and/or impacts that are few in number, generally site-specific, largely reversible and readily addressed through mitigation measures.
Category C – Projects with minimal or no adverse environmental and social risks and/or impacts.
Designated Countries are those countries deemed to have robust environmental and social governance, legislation systems and institutional capacity designed to protect their people and the natural environment.
Project-related Refinance & Project-related Acquisition For Project Finance
Total number that reached Financial Close in the reporting period: 2
| Sector | |
|---|---|
| Mining | |
| Infrastructure | |
| Oil & Gas | |
| Power | 2 |
| Others | |
| Sub-Total | 2 |
| Region | |
|---|---|
| Americas | 2 |
| Europe, Middle East & Africa | |
| Asia Pacific | |
| Sub-Total | 2 |
| Country Designation | |
|---|---|
| Designated Country | |
| Non Designated Country | 2 |
| Both | |
| Sub-Total | 2 |
Project Name Reporting For Project Finance (And Project-related Refinance & Project-related Acquisition Finance For Project Finance)
| No. | Project Name | Sector | Project Location(s) | Year of Financial Close |
|---|---|---|---|---|
| 1 | RABIGH 2 Solar PV Project | Power | Saudi Arabia | 2025 |
| 2 | SHUWEIHAT 1 Extension Project | Power | United Arab Emirates | 2025 |
| 3 | Project Suwayama | Others | Japan | 2025 |
| 4 | Hachimori Wind Firm,Toyohata West Wind Farm,Nohejimachi-North Wind Farm,Noheji Mukaida Wind Farm | Power | Japan | 2025 |
| 5 | Qurayyah IPP Expansion | Power | Saudi Arabia | 2025 |
| 6 | The Haweswater Aqueduct Resilience Programme | Infrastructure | United Kingdom | 2025 |
| 7 | PV4 Al Khazna Project | Power | United Arab Emirates | 2025 |
| 8 | FRESHWATER SOLAR | Power | United States | 2025 |
| 9 | BISHA Photovoltaic Project | Power | Saudi Arabia | 2025 |
| 10 | HUMAIJ Photovoltaic Project | Power | Saudi Arabia | 2025 |
| 11 | KHULIS Photovoltaic Project | Power | Saudi Arabia | 2025 |
| 12 | Starah Wind Farm Project | Power | Saudi Arabia | 2025 |
| 13 | Shaqra Wind Farm Project | Power | Saudi Arabia | 2025 |
| 14 | Round 4 Yanbu Wind Project | Power | Saudi Arabia | 2025 |
| 15 | Haute-Chaudière | Power | Canada | 2025 |
Number of projects that were not disclosed as per the disclosure conditions specified in Annex B of the Principles: 3
Under EP4, project name reporting is required for Project Finance transactions that have reached Financial Close and encouraged for Project-Related Corporate Loans that have reached Financial Close.
Project-Related Corporate Loans
Total number that reached Financial Close in the reporting period: 2
| Equator Principles Category | A1 | B2 | C3 |
|---|---|---|---|
| Sector | |||
| Mining | |||
| Infrastructure | |||
| Oil & Gas | |||
| Power | 1 | ||
| Others | 1 | ||
| Region | |||
| Americas | |||
| Europe, Middle East & Africa | 1 | ||
| Asia Pacific | 1 | ||
| Country Designation | |||
| Designated Country 4 | 1 | ||
| Non Designated Country | 1 | ||
| Both | |||
| Independent Review | |||
| Yes | 1 | ||
| No | 1 | ||
| Totals | 1 | 1 | |
Category A – Projects with potential significant adverse environmental and social risks and/or impacts that are diverse, irreversible or unprecedented.
Category B – Projects with potential limited adverse environmental and social risks and/or impacts that are few in number, generally site-specific, largely reversible and readily addressed through mitigation measures.
Category C – Projects with minimal or no adverse environmental and social risks and/or impacts.
Designated Countries are those countries deemed to have robust environmental and social governance, legislation systems and institutional capacity designed to protect their people and the natural environment.
Project-related Refinance & Project-related Acquisition For Project-related Corporate Loans
Total number that reached Financial Close in the reporting period: 0
Project Name Reporting For Project-related Corporate Loans (And Project-related Refinance & Project-related Acquisition For Project-related Corporate Loans)
| No. | Project Name | Sector | Project Location(s) | Year of Financial Close |
|---|---|---|---|---|
| 1 | Round 4 Yanbu Wind Project | Power | Saudi Arabia | 2025 |
Number of projects that were not disclosed as per the disclosure conditions specified in Annex B of the Principles: 1
Under EP4, project name reporting is encouraged for Project-Related Corporate Loans that have reached Financial Close and required for Project Finance transactions that have reached Financial Close.
EP4 applies for those transactions mandated after 1 October 2020 and that have reached Financial Close by the end of the period being reported.
Implementation of the Equator Principles
Sumitomo Mitsui Trust Bank´s EP implementation reporting: https://www.smtg.jp/english/sustainability/initiatives/equator